Construction worker standing near a retaining wall

Choosing the right concrete pump

Core filling block walls with a concrete pump

Stage 1 of 3
Before you book
Read time
12 min
Published
Sources
8 cited

In brief

Adbri Masonry's North Queensland guide puts a standard 200 series Besser block at about 0.66 m3 of grout per 100 blocks, and lists 0.100 m3 per square metre of wall as a separate figure. Tell the supplier the concrete is for filling blockwork, have the cores cleaned and the clean-outs closed before the pump arrives, and fill tall walls in stages.

On this page

Core filling a block wall: the short answer

Core filling a block wall means filling the hollow cores of the concrete blocks with grout once the wall is laid and the steel is in. National Masonry describes grout as highly workable concrete, and says it can be mixed on site and poured from buckets into hoppers on top of the wall or, for larger jobs, delivered by transit mixer and pumped into the cores using a small nozzle on the hose. The quantity comes from the block maker's own table: Adbri Masonry's North Queensland guide lists about 0.66 m3 of grout for every 100 standard 200 series blocks. Everything structural about a core filled wall, including the grout specification, the reinforcement and how high each lift can go, belongs to the engineer and the block manufacturer. This guide covers the practical side of a pumped core fill: working out the volume, ordering it, getting the wall ready for the pump, and what happens on pour day. Block fills are on the list of work Far Northern Concrete Pumping pumps.

What a cored concrete block is: hollow cores for steel and grout

A cored concrete block is a hollow masonry block, often called a Besser block, with open vertical cores running through it. National Masonry explains that concrete blocks in 140, 190 and 290 mm widths have large cores so steel reinforcing rods can be placed in them and grout poured or pumped in around the steel. How much of the wall gets filled depends on the design. National Masonry says a wall reinforced with bars at 800 mm centres or less and fully grouted is called reinforced masonry. A partially reinforced wall is only grout filled where the reinforcement is placed, usually in bond beams and in the vertical cores holding steel. That difference changes the order a lot: a fully grouted wall fills every core, while a partially reinforced one fills only some. National Masonry also states that all reinforced walls must be designed by a structural engineer, so the plans will show which cores are filled.

How much concrete a block wall takes: about 0.66 m3 per 100 standard 200 series blocks

A standard 200 series block wall takes about 0.66 m3 of grout per 100 blocks, according to Adbri Masonry's North Queensland Besser block guide, which also lists about 0.100 m3 per square metre of wall. The two columns are separate figures and give slightly different totals for the same wall, so work from whichever one matches how you are measuring. The Concrete Masonry Association of Australia says block makers usually publish a "blocks filled per cubic metre" table and to ask your supplier for it, because core sizes differ between products. The table below repeats Adbri Masonry's North Queensland figures, which are approximate and apply to those blocks only.

Volume of grout used in filling cores, Adbri Masonry North Queensland Besser blocks (manufacturer's approximate figures)

Volume of grout used in filling cores, Adbri Masonry North Queensland Besser blocks (manufacturer's approximate figures)
BlockPer m2 of wallPer 100 blocksBlocks filled per m3
15.01 / 15.42 (150 series)0.054 m30.43 m3About 220
20.01 / 20.42 (200 series)0.100 m30.66 m3About 150
20.48 H block (200 series)0.100 m30.80 m3About 120
30.48 (300 series)0.180 m31.44 m3About 69

Two worked examples show the sums. A fully filled 200 series wall 10 m long and 1.6 m high is 16 m2, and 16 x 0.100 gives about 1.6 m3. A job of 300 standard 200 series blocks is 3 x 0.66, about 2.0 m3, while 300 H blocks is 3 x 0.80, or 2.4 m3. On a partially reinforced wall, count only the blocks whose cores are being filled. Other makers' tables come out close but not identical: National Masonry's design guide lists about 150 of its 20.01 standard blocks and about 125 of its 20.48 H blocks per cubic metre of grout, and 50 of its 40.925 pier blocks. Use the table for the block on your plans. For slabs and footings poured at the same time, our guide to how much concrete you need covers rectangular volumes.

Ordering core fill: tell the supplier it is for filling blockwork

When ordering core fill, tell the concrete supplier the mix is for filling blockwork and that it will be pumped. Adbri Masonry's Versaloc brochure advises using ready-mixed core fill where possible and specifying, when ordering, that it is for filling blockwork. Holcim says that to design a mix it needs to know the placement method, such as a pump, the type of pump and the size and length of the line. You or your builder order the concrete from the premix supplier; we supply the pump in between. The grade itself is not a site decision. National Masonry says the correct grout specification is critical to achieving the structural design of a reinforced wall, and lists compliance with AS 3700 Clause 10.7 and a pouring consistency that fills the cores completely. The Concrete Masonry Association of Australia adds that grout is not mortar: it must flow freely to surround the steel and completely fill the cores.

  • The grout specification from the engineer's drawings or the block manufacturer.
  • That the concrete is for filling blockwork, and the block series being filled.
  • The volume, worked out from the block maker's table.
  • That it will be pumped, plus the pump type and the size and length of the line (ask us for these when you book).
  • The delivery timing, if the wall will be filled in stages.

Our guide to pump mix concrete explains what a supplier changes in a mix so it travels through a pump line.

Why a pump suits core filling: the grout goes in through a small nozzle

A concrete pump suits core filling because the grout has to go into narrow cores along the top of the wall, and a hose with a small nozzle can be moved from core to core along the top of the wall. National Masonry describes exactly that for larger jobs: grout delivered by transit mixer and pumped into the cores through a small nozzle on the hose, in place of buckets and hoppers. A line pump uses flexible hoses that work through tight spaces, and suits residential and small commercial jobs, which fits many block walls on tight sites. As well as our standard line pump, we run a compact high-pressure line pump for hard-to-reach pours. Where the wall is high or the truck cannot get close, a boom pump places concrete through a folding arm that can reach over a house, fence or landscaping. We run 31 m, 28 m and 20 m boom pumps. We pump block fills and structural walling on commercial jobs as well as homes. Our line pump vs boom pump guide compares the two set-ups.

Before the pump arrives: clean cores, steel tied, clean-outs closed

The wall has to be ready before the pump is booked to start. National Masonry's design guide sets out the sequence for its core-fill blocks, and Adbri Masonry's North Queensland range includes a 200 series clean out block and clean out tile.

  1. Knock off mortar dags: National Masonry has a steel rod pushed down each core to knock off mortar projecting into it and to break up mortar dropped onto the footing.
  2. Clear the debris: the cores are hosed or swept out from the bottom of each core through the clean-out space.
  3. Tie the steel: the vertical steel rods are tied to the starter bars.
  4. Close the clean-outs: the clean-out blocks are covered with formwork, ready for grouting. On low walls, National Masonry describes leaving a gap in the mortar bed at the bottom of each core and hosing out the dropped mortar before it sets.
  5. Cool the blocks on hot days: National Masonry says hot weather may call for hosing the cores with water to stop the grout flash-setting, finished at least 30 minutes before the grout goes in.
  6. Book any inspection your engineer or certifier wants before the cores are filled, because the steel cannot be seen afterwards.

Pour day: fill in lifts and clean the wall as you go

Pour day for a block wall is usually staged, because fresh grout pushes hard on the bottom of the cores. National Masonry says lifts of more than 1.2 metres should not be grouted in one pour, and that above 1.2 metres it is preferable to fill the cores in two stages at least 30 minutes apart. For its 150 series blocks it reduces lifts to 800 mm, or four courses, so no voids are left. Adbri Masonry strongly recommends a maximum filling height between pours of 1.8 m, or nine courses, for its Versaloc walls. These are each manufacturer's figures for its own blocks; your engineer's lift heights come first. The same pressure forces water out through the face of the wall. For its Designer Range and face blocks, National Masonry says seepage must be cleaned off and spills cleaned before they set, and it says every core-filled wall must be cleaned thoroughly straight after filling so lime leaching from the core fill does not stain the blockwork. Have a hose and brushes ready before the first lift.

How long the whole job takes depends on the volume, the number of lifts and the waits between them; our guide to how long a concrete pour takes covers the other factors.

Common problems on core fill pours

The table below pairs each common problem with what the manufacturer or WorkSafe Queensland says about preventing it.

Common core fill problems and how the sources say to prevent them

Common core fill problems and how the sources say to prevent them
ProblemLikely causePrevention
Cores not filling to the bottomMortar dags and droppings in the coresRod and clean every core through the clean-outs before the pour (National Masonry)
Pump line blocksA mix that is not a pumpable mix as specified by the supplierOnly pump a pumpable mix as specified by the supplier; WorkSafe Queensland warns other concrete can block the line and cause hose whip
Lumps stopping the nozzleContaminating lumps in the groutAdbri Masonry says grout should be free of lumps larger than 15 mm, which may need a screen over the pump hopper
Hose blockage at the wallA kinked discharge hoseWorkSafe Queensland notes a kinked flexible hose can block, depending on the mix design and aggregate size
Voids in the wallLifts too high for the blockFill in the stages the engineer and manufacturer set (National Masonry: 800 mm lifts for 150 series)
Stained face blockworkSeepage and spills left to setClean the wall straight after filling (National Masonry)

Our guide to concrete pump blockages covers line blockages in more detail.

Compaction, grade and lift heights come from the engineer

Whether core fill is vibrated, rodded or simply poured is part of the engineer's specification, and this guide does not set a method. What the industry sources agree on is the result the grout must achieve. The Concrete Masonry Association of Australia says grout must be of pouring consistency because filling the cores matters more than high grout strength. National Masonry's specification calls for a pouring consistency that fills the cores completely and surrounds the reinforcement without the mix separating. Adbri Masonry describes a cohesive mix as one with no tendency to segregate when pumped down into the wall. If your drawings say how the grout is to be compacted, follow them; if they do not, ask the engineer before pour day rather than deciding on site.

Next steps

If you are still choosing a pump for the wall, our line pump vs boom pump guide compares access, reach and set-up. For round pier holes on the same job, see how much concrete for post holes. Far Northern Concrete Pumping is based in Mareeba and pumps block fills for commercial and residential jobs across Cairns and the Tablelands. See our equipment, then contact us or call 0413 345 977 with the location, the type of pour and the volume your concrete supplier has quoted.

Sources

  1. Besser Block and Brick Guide: North Queensland, Adbri Masonry. Accessed 30 October 2026.
  2. Versaloc Walling System brochure, Adbri Masonry. Accessed 30 October 2026.
  3. Masonry Blocks and Bricks Design Guide: South QLD and NSW, National Masonry. Accessed 30 October 2026.
  4. Technical FAQs, Concrete Masonry Association of Australia. Accessed 30 October 2026.
  5. 5 Essential Things You Need to Know When Ordering Premixed Concrete, Holcim Australia. Accessed 30 October 2026.
  6. Concrete Pumping Code of Practice 2019, WorkSafe Queensland. Accessed 30 October 2026.
  7. Design Manual D2: Site Regrading (FNQROC Development Manual), Far North Queensland Regional Organisation of Councils. Accessed 30 October 2026.
  8. Fences & landscaping, Cairns Regional Council. Accessed 30 October 2026.

Frequently Asked Questions

How much core fill do I need for 100 blocks?

It depends on the block. Adbri Masonry's North Queensland guide lists about 0.66 cubic metres of grout per 100 standard 200 series blocks, 0.80 for 200 series H blocks, 0.43 for 150 series blocks and 1.44 for 300 series blocks. Count only the blocks whose cores are being filled, and check the table for the exact block on your plans, because each maker publishes its own figures.

Can you use a line pump to core fill blocks?

Yes. National Masonry describes pumping grout into the cores through a small nozzle on the hose for larger jobs, and a line pump's flexible hoses suit tight spaces and residential or small commercial work. Where the wall is high or hard to reach from the street, a boom pump can place the grout from its arm instead. Tell us the wall height and access when you book.

What should I tell the concrete supplier when ordering core fill?

Say it is for filling blockwork, as Adbri Masonry advises, and give the grout specification from the engineer's drawings and the volume from the block maker's table. Tell them it will be pumped: Holcim says a supplier designing a mix needs the placement method, the type of pump and the size and length of the line. If the wall is filled in stages, agree delivery timing too.

How long does it take to core fill a block wall?

It depends mostly on the volume and the number of lifts. Tall walls are not filled in one go: National Masonry says lifts over 1.2 metres should be filled in two stages at least 30 minutes apart, and its 150 series blocks drop to 800 mm lifts. Your engineer's lift heights apply first. Add time to rod and clean the cores beforehand and wash down the wall afterwards.

Do you need to vibrate core fill?

Compaction is set by the engineer, so check the drawings. The industry sources focus on flow: the Concrete Masonry Association of Australia says grout must be of pouring consistency because filling the cores matters more than high strength, and National Masonry's specification calls for a consistency that fills the cores completely and surrounds the steel without separating. If the drawings are silent, ask the engineer before pour day.

Does a core filled retaining wall need an engineer?

For land development and subdivision works, the FNQROC Development Manual (D2) requires retaining walls over 1.0 m high to be designed, detailed and certified by a structural engineer. National Masonry also says all reinforced block walls must be designed by a structural engineer. Cairns Regional Council recommends asking a private building certifier whether your project needs approval before you build.

Do you pump block fills around Cairns and the Tablelands?

Yes. Block fills are on the list of work we pump, and we work from our base in Mareeba across Cairns and the Tablelands. Our operators have access to a line pump, a compact high-pressure line pump and 31 m, 28 m and 20 m boom pumps. Call 0413 345 977 with the location, the type of pour and the volume your supplier has quoted.